Bridge On Target to Meet Goal
By John T. Ryan
Bridge Construction Superintendent Chad Fancher had a broad smile today as he watched Noel J. Brunell personnel pave the approaches to the Jarvis Road Bridge. Obviously very proud of the structure, Fancher looked at the bridge and remarked, “It looks pretty good doesn’t it.”
Fancher has good reason to be smiling. If good weather prevails he believes that the bridge will meet his self-imposed goal of September 15th. It may even be finished on September 13th. According to the contract terms he has at least until the end of October to complete the project. Construction began on June 12th.
Guardrails leading to the bridge, grass planted and signs still have to finished, but Fancher is confident he will make his goal.