Good News for Many Peru residents
By John T. Ryan
Peru – Natural gas lines were installed in most of the Peru hamlet several years ago. For some unknown reason they were not installed along a few streets. Thankfully, that era is coming to an end. Over the past few weeks NYSEG has installed gas lines on McIntosh Drive, Birchwood Avenue and McDonald Place. Gas is currently available on those streets. This week lines were installed along Maiden Lane and Locust Drive. Next week work will take place on a small portion of Maiden Lane and Holden Avenue. In ten to fourteen days the contractor will begin installation of 8,000+ feet of gas lines along the Laphams Mills Road.
Several residents have ordered gas installation. Job Supervisor Frank LaBombard said more people typically order when they see neighbors hooking up. NYSEG installs lines up to a resident’s meter. Installation within a home or business is the owner’s responsibility.
Posted: August 24th, 2018 under Peru News, Peru/Regional History.